PPT Slide
Today -
Tooling
- These tools have multiple edges - changing the cost structure considerably:
- PCD cost per edge - apx. $100.00
- CVD cost per edge - apx. $15.00
-
- In the Brake Rotor example sited earlier, the cost per day of PCD tools was estimated at
$2048.
- 45.5 tools per day in the example operation (single edge/tool)
- in93 the cost per insert used was $70 (up to $100/insert today)
- a regrind charge of $20 was included
- In the same way, the cost per day for CVD tools would be:
Notes:
- This shows what would happen if only the cost of the tool changed.
- Is there machining advantage to these tools?
- Higher speeds? Greater Material Removal Rate? Longer life?
- Further testing is needed to answer these questions.
- It can be said that these tools are less expensive per edge.